Completed Project
31 Jul 2025
Internal connection to Knauf industry-Mkuranga
This project commenced on 21st March 2025, with an implementation period of three months. The project was completed on 22nd June 2025 and officially handed over to the client on 8th July 2025. The main objective was to carry out internal natural gas infrastructure connection to the KNAUF GYPSUM INDUSTRY in Mkuranga. GASCO executed the works with high technical standards and strict adherence to safety, regulatory compliances and quality standards.


Photos: Welding activities on progress at KNAUF FACTORY