Project Details
Completed Project 27 Oct 2026

Engineering, Procurement and Construction (EPC) for Natural Gas interconnection to KIBO Development Industries in Mkuranga

Engineering, Procurement and Construction (EPC) for Natural Gas interconnection to KIBO Development Industries in Mkuranga

GASCO entered into a contract with KIBO Development Industries in Mkuranga for undertaking Engineering, Procurement and Construction (EPC) for gas pipeline interconnection to the industries. The project commenced on 2nd March,2026 with a contract period of six months. The project includes construction of 125mm HDPE pipeline at a distance of 0.1Km and installations of Pressure Reduction Station (PRS), testing and commissioning of the installed gas network. The project was successfully completed on 10th July,2026.

Picture: Gas Pipe Construction works to KIBO industry