Completed Project
27 Oct 2026
Engineering, Procurement and Construction (EPC) for Natural Gas interconnection to Brilliant Sanitary Ware Factory in Mkuranga
GASCO entered into a contract with Brilliant Sanitary Ware factory in Mkuranga for undertaking Engineering, Procurement and Construction (EPC) for gas pipeline interconnection to the factory. The project commenced on 18th March,2026 with a contract period of six months.
The project includes construction of 250mm HDPE pipeline at a distance of 1.2Km and installations of Pressure Reduction Station (PRS), testing and commissioning of the installed gas network. The project was successfully completed on 28th August,2026.
;

Picture: Butt Fusion works and pressure regulator setting at BRILLIANT Sanitary ware company