The United Republic of Tanzania
Ministry of Energy

Gas Company (Tanzania) Limited

Engineering, Procurement and Construction (EPC) for Natural Gas interconnection to TANHealth CNG Station-Mbezi beach

Posted On: 31 July, 2025
Engineering, Procurement and Construction (EPC) for Natural Gas interconnection to TANHealth CNG Station-Mbezi beach

This project involves the execution of Engineering, Procurement, and Construction (EPC) works for the natural gas interconnection to the TANHealth Compressed Natural Gas (CNG) Station located at Mbezi Beach, Dar es Salaam. The contract was signed on 20th February 2025 with a planned implementation period of four months. Site activities officially commenced on 28th June 2025.

As of now, the project has reached 54.15% completion, with procurement of a key long-lead item (FMS skid) still in progress. The project is expected to be completed by 30th September 2025. This initiative is part of GASCO’s broader mission to expand access to compressed natural gas as a clean and sustainable energy source for transport and other applications.